Build Conex
1800 868 548

Case Studies & Lessons Learned

Urban Rail Project – Change Process Misuse

Urban Rail Project – Change Process Misuse

On a major urban rail EPC, a 540-day delay claim blamed Employer Change Notices, but forensic analysis showed the real driver was replacing the original design house and misusing the contractual change process. Mapping 36 CNs to the critical path reframed the dispute around internal design and process failures, not cumulative change.

Warehouse Automation – Delivery-Model Misalignment

Warehouse Automation –
Delivery-Model Misalignment
A principal technology provider’s standard teaming model was undermined when a newcomer package was let on conventional lump-sum terms. Misaligned contract and site controls led to disputes, underscoring lessons on briefing teams, supporting PMs commercially, and managing any departures from the agreed delivery model.
Wind Farm Electrical –  
As-Built Misalignment

Wind Farm Electrical –  As-Built Misalignment

On a large wind farm, outdated OEM manuals and pre-wired turbine masts clashed with site conditions, driving significant re-wiring and access impacts. Mapping manual versus as-built conditions enabled hour-based valuation of variations and reinforced early treatment of documentation-driven change.
Defence Wharf Redevelopment

Defence Wharf Redevelopment

This case study relates to a concrete and formwork subcontractor engaged on a major Defence wharf redevelopment in the Northern Territory. The subcontract scope included formwork, reinforcement, concrete supply and placement, and finishing for key wharf elements, including the main wharf decks and mooring dolphin structures.

Forensic Labour Hours Reconciliation and Adjudication Defence Aquatic Centre

Concrete and Construction: Forensic Labour Hours Reconciliation and Adjudication Defence Aquatic Centre
Our client was engaged on the Mount Morgan Aquatic Centre project to perform concrete and associated construction works, with labour supplied on the basis of daily timesheets and job records and (given the location and crew movements) compensable travel and associated allowances forming part of the commercial reality of the delivery model.

Ceilings and Partitions Extension of Time and Disruption Claim

Ceilings and Partitions Extension of Time and Disruption Claim
This case study concerns claims support for a specialist interior linings subcontractor engaged to deliver the ceilings and partitions package on an industrial/logistics development at Wacol, Queensland. The subcontract scope included framing, plasterboard linings and setting across multiple zones, including Office 1, Office 2, dock offices, truck amenities, a pump room and common areas.

Forensic Quantum and Delay Assessment on a $13.6 Million Automated Distribution Facility Project

Forensic Quantum and Delay Assessment on a $13.6 Million Automated Distribution Facility Project
A leading law firm engaged Albert Merolla of Build Conex to act as independent quantum and delay expert in a complex $13.6 million dispute over payment, variations, and delay. The case involved an automated distribution facility where the subcontractor and principal contractor disagreed over cost entitlements and project delays.

Successful Defence of QCAT Building Dispute – Claim Withdrawn

Ceilings and Partitions Extension of Time and Disruption Claim
Baker Merz Lawyers recently acted for a residential builder in a Queensland Civil and Administrative Tribunal (QCAT) building dispute concerning renovation works at a residential property in Teneriffe, Brisbane.

Request an initial dispute scoping discussion.

CCPM Delay AnalysisCCPM Delay Analysis
© 2026 Build Conex | BUILDCON QUANTUM AND DELAY EXPERTS PTY LTD | ACN 689 667 356 | Liability Limited by a scheme under professional standards legislation
phone-handset