Build Conex
1800 868 548

Lessons Learned: Documentation As-Built Miss-Alignment (Wind Farm Electrical)

Background

The dispute involved a large-scale wind farm where turbines had been updated and delivered with pre-wired masts suitable for the previous model. Substantial re-wiring occurred onsite. We were engaged independently to opine on entitlement and quantum under an electrical installation subcontract.

The delivery model

The subcontract bundled an OEM Installation Manual and priced change mechanisms via dayworks with valuation by hours and site allowances rather than re-measurement, so that genuine departures could be costed contemporaneously. The manual material provided was for the older turbine variant.
Documentation As-Built Miss-Alignment (Wind Farm Electrical)

Where things diverged (on the documents)

Field conditions repeatedly conflicted with the manual: hoist access constraints; LV earth bar located under floor plates (confined-space terminations); UPS installed one level higher and factory pre-wiring incorrect; transformer–converter cables supplied at mismatched lengths; cable-tray path had to be re-worked by rope access inside the mast; cable bundles increased (6→7) and diameters up-sized; armour-casting sheathing missing from the kit; site allowance impacts followed.

What our engagement added

We mapped manual vs as-installed conditions and valued discrete tasks under Schedule E—testing claimed hours against trade-level effort and access constraints—then rolled up allowances. Examples: hoist access hours; UPS rewiring 4 h/WTG; transformer–converter cable corrections; site allowance in man-days. We explained why these were scope changes (not mere productivity).

Practical takeaways

  • Treat OEM deviations as variations early, not as “efficiency” issues.
  • Lock a simple, hour-based pathway (rate + allowance) for document-driven changes and keep signed field directions.
  • De-risk access: plan for hoist/rope-access when cabinet locations/levels differ from drawings.
  • Where factory pre-wiring/cable sets vary, pre-agree a rectification matrix (hours per WTG) to avoid serial disputes.

Note: In the material reviewed, our report reframed the dispute around documentation–as-built divergence, enabling clean, rate-based resolution rather than a productivity argument.

Discover how we solve Complex Disputes
See More Case Studies 
Albert Merolla
Need an Expert?
Contact Us to Discuss

Lock
We respect your privacy
We reserve the right to determine whether, how, and when to respond to any calls, emails, or other enquiries. We will only respond to enquiries that are appropriate for the nature of our work. No initial discussion should be taken as an acceptance of instructions or the formation of a solicitor-client relationship.

Explore how we can deliver a solution tailored to your project.

CCPM Delay AnalysisCCPM Delay Analysis
© 2026 Build Conex | BUILDCON QUANTUM AND DELAY EXPERTS PTY LTD | ACN 689 667 356 | Liability Limited by a scheme under professional standards legislation
phone-handset