The dispute involved a large-scale wind farm where turbines had been updated and delivered with pre-wired masts suitable for the previous model. Substantial re-wiring occurred onsite. We were engaged independently to opine on entitlement and quantum under an electrical installation subcontract.
The subcontract bundled an OEM Installation Manual and priced change mechanisms via dayworks with valuation by hours and site allowances rather than re-measurement, so that genuine departures could be costed contemporaneously. The manual material provided was for the older turbine variant.
Field conditions repeatedly conflicted with the manual: hoist access constraints; LV earth bar located under floor plates (confined-space terminations); UPS installed one level higher and factory pre-wiring incorrect; transformer–converter cables supplied at mismatched lengths; cable-tray path had to be re-worked by rope access inside the mast; cable bundles increased (6→7) and diameters up-sized; armour-casting sheathing missing from the kit; site allowance impacts followed.
We mapped manual vs as-installed conditions and valued discrete tasks under Schedule E—testing claimed hours against trade-level effort and access constraints—then rolled up allowances. Examples: hoist access hours; UPS rewiring 4 h/WTG; transformer–converter cable corrections; site allowance in man-days. We explained why these were scope changes (not mere productivity).
Note: In the material reviewed, our report reframed the dispute around documentation–as-built divergence, enabling clean, rate-based resolution rather than a productivity argument.