Build Conex
1800 868 548

Forensic Quantum and Delay Assessment on a $13.6 Million Automated Distribution Facility Project – Court Accepted Expert Evidence and Awarded Full Entitlement

Summary

A leading law firm engaged Albert Merolla of Build Conex to act as independent quantum and delay expert in a complex $13.6 million dispute over payment, variations, and delay.

The case involved an automated distribution facility where the subcontractor and principal contractor disagreed over cost entitlements and project delays. The matter proceeded before the Supreme Court of New South Wales, with competing claims under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Albert’s independent forensic assessment of both time and cost provided the clarity needed for the Court to make a determination. His findings were accepted in full, and the subcontractor was awarded the full claimed amount, including interest and legal costs.

The result was later upheld on appeal.

Project Overview

Detail Description
Industry Industrial automation and logistics infrastructure
Location New South Wales
Contract Type Fixed-sum subcontract
Dispute Type Delay, disruption, variation valuation, and payment under contract
Expert Services Provided Forensic quantum and delay analysis, expert report, and testimony
Legal Context Building and Construction Industry Security of Payment Act 1999 (NSW)
Outcome Expert evidence accepted; judgment and appeal both decided in favour of subcontractor
This case demonstrates how a disciplined, data-driven forensic approach to time and cost can clarify complex disputes and support a successful legal outcome.

Situation Before

Before Build Conex became involved, the project had reached an impasse.

The subcontractor and principal each alleged that the other was responsible for delay and cost escalation. Variation approvals were inconsistent, progress assessments differed, and both parties advanced competing interpretations of entitlement.

For the law firm, the challenge was to establish factual clarity and quantify the true financial position. Without a credible expert analysis, the case risked becoming a battle of conflicting opinions.

Albert was engaged to provide an independent and objective assessment of the facts to determine the real cause of delays, the value of work performed, and whether payments already made were aligned with verified progress.

Services Build Conex Performed

Albert’s analysis brought together technical, commercial, and evidentiary expertise to create a single, consistent narrative for the Court.

Build Conex services included:

  • Reviewing all project and contractual documentation to understand the commercial and operational background.
  • Analysing schedules, progress records, and cost data to identify key delay events and quantify their impact.
  • Assessing payment and variation records to verify what was completed, claimed, and paid.
  • Preparing a clear, court-ready report that explained complex construction and financial issues in straightforward language.
  • Providing expert evidence and participating in conclaves to assist the Court in understanding the technical aspects of the dispute.

Key outcomes of the analysis:

  • Demonstrated that project delays were driven primarily by changes in sequencing and information release, not by poor performance.
  • Reconciled over $14 million in claimed works, verifying progress and payment with factual evidence.
  • Identified overpayments of approximately $960,000, establishing the financial position clearly.
  • Provided a verified entitlement of $884,570 (incl. GST) under the Security of Payment Act—an amount later upheld in judgment.

Albert’s findings reduced ambiguity, resolved conflicting interpretations, and provided counsel with reliable, fact-based evidence that aligned with the Court’s expectations.

Outcome for Client

The Supreme Court of New South Wales accepted Albert’s expert evidence as independent, well-reasoned, and supported by documentation.

The Court found that the principal contractor’s payment schedule did not meet statutory requirements and that the subcontractor’s claim was properly substantiated by the expert analysis.

Outcome Result
Quantum Accepted by Court $884,570 (incl. GST)
Overpayment Identified ~$960,000 (beyond verified progress)
Judgment In favour of subcontractor
Appeal Outcome Upheld – findings accepted
Final Result Full entitlement and costs awarded

Albert’s findings provided the court with a clear evidentiary path, allowing a complex technical dispute to be resolved on the strength of verified data rather than competing assertions.

Key Insights for Construction Lawyers and Barristers

This case highlights several important insights for construction law practitioners and dispute resolution professionals.

1. Independent Expert Evidence Clarifies Complex Facts
When contractual and factual narratives diverge, an independent expert provides the structured, objective analysis that courts require to make findings with confidence.

2. Integration of Time and Cost Strengthens the Argument
Combining schedule and quantum analysis creates a unified evidentiary picture, ensuring that delay events and financial impact are linked logically and consistently.

3. Early Engagement of Experts Saves Time and Cost
Involving a forensic expert early in a dispute helps legal teams identify the strongest arguments, test factual claims, and streamline proceedings.

4. Independence Builds Credibility
Experts who demonstrate transparency, restraint, and neutrality enhance the weight of the evidence and strengthen counsel’s position before the Court.

5. Clear Communication Wins Cases
Technical complexity can obscure truth. Reports that present clear reasoning, supported by verifiable data, are far more persuasive than analysis overloaded with detail.

Conclusion

This matter demonstrates how independent forensic analysis can determine the direction of complex construction disputes. Albert’s ability to integrate engineering, scheduling, and financial expertise allowed the Court to rely on clear, impartial evidence. His work provided the factual structure the legal team needed to argue successfully and achieve a decisive outcome.

For law firms and barristers handling high-value construction disputes, Build Conex delivers the kind of independent, court-trusted expertise that transforms complex data into credible, actionable evidence.

Confidential Enquiry

For confidential discussions regarding upcoming litigation, arbitration, or adjudication requiring independent quantum or delay analysis, contact Albert Merolla at Build Conex.

All enquiries are handled personally and in strict confidence.

Discover how we solve Complex Disputes
See More Case Studies 
Albert Merolla
Need an Expert?
Contact Us to Discuss

Lock
We respect your privacy
We reserve the right to determine whether, how, and when to respond to any calls, emails, or other enquiries. We will only respond to enquiries that are appropriate for the nature of our work. No initial discussion should be taken as an acceptance of instructions or the formation of a solicitor-client relationship.

Explore how we can deliver a solution tailored to your project.

CCPM Delay AnalysisCCPM Delay Analysis
© 2026 Build Conex | BUILDCON QUANTUM AND DELAY EXPERTS PTY LTD | ACN 689 667 356 | Liability Limited by a scheme under professional standards legislation
phone-handset